Not Your Typical Equipment Delivery: Getting a 52,000-Pound Loader Nearly 7,000 Feet Underground

Moving a 52,000-pound loader is a big job. Getting it nearly 7,000 feet underground takes a little more planning.

That’s what crews from Redpath USA and Resolution Copper recently accomplished, lowering a Caterpillar R1300 underground loader through No. 10 Shaft to support ongoing development work on 68 Level.

The Cat R1300 is designed to load, haul and move rock through underground tunnels. But before it could get to work, crews had to figure out how to get a machine that size down a vertical mine shaft.

And it wasn’t going down in one piece.

The Work Starts Long Before the Lift

Moving equipment this size underground isn’t as simple as hooking it to a cable and lowering it down.

The crew had to account for the loader’s size, weight and the limited space inside the shaft. Engineers developed a plan to separate the machine into sections that could be safely lifted and lowered underground.

For JR Villalobos, a Senior Toplander with Redpath at Resolution Copper, preparation and experience are essential.

“Something like this takes hours and hours of planning. We want to make sure that everything is done safely, experience is very important when working on a job like this.”

The operation brought together engineers, mechanics, riggers, toplanders and hoist operators. Each had a specific role, from preparing the machine and securing the loads to operating the hoist and receiving the equipment underground.

Making a Big Machine Fit

The lift plan called for moving the loader underground in three pieces.

The largest was the rear section, weighing approximately 28,700 pounds. The front section weighed another 18,600 pounds, and the bucket weighed about 5,000 pounds.

Each piece required its own preparation and rigging before it could be lowered. Crews had to carefully position and secure the equipment, accounting for its weight, balance and the available space inside the shaft. Even small adjustments mattered when moving components weighing several tons through a confined vertical opening.

Much of that work happened before the first piece ever left the surface.

A Long Way Down

No. 10 Shaft extends nearly 7,000 feet underground, providing access to the areas where Resolution Copper’s exploration and development work is taking place.

For this move, the hoist operator controlled the lowering process from the surface while crews coordinated the equipment’s movement through the shaft. Team members stationed at the surface and underground monitored the operation, communicated with one another and prepared to receive each section at its destination.

For Michael Armijo, a Toplander with Redpath, that kind of work comes down to trusting the people around you. “This wouldn’t work if we didn’t have teamwork. We’ve got to trust each other.”

The Job Doesn’t End at the Bottom

Getting the loader down the shaft was only part of the job.

Once the sections reached 68 Level, crews had to safely receive and move them into position underground. The components removed for transport would then need to be reassembled and the mechanical systems checked before the loader could be placed into service.

Once operational, the Cat R1300 will help crews load and move rock and other material as underground development continues.

Redpath led the equipment move, with support from Resolution Copper personnel.

For AJ Quiroz, Mine Operations Superintendent at Resolution Copper, completing the move was a significant accomplishment for everyone involved.

“Today went well, nothing went wrong. This is a huge success for the team, and the project, it’s something to celebrate for sure. It’s game time for us, as miners.”

With the loader now on 68 Level, crews have another piece of equipment in place to support the underground work ahead.